Confirmed 20 Nov 2026 · Governance A one-minute read
Korea proposes exempting regional AI data centres up to 50 megawatts from grid review.
The draft decree went out for comment on November 20, closing December 30. Caveat: it is a proposal, and the capital region keeps the review it already has.
Korea's grid review was the bottleneck on every new AI site.
Below 50 megawatts and outside Seoul, the review disappears.
Why it matters
The numbers explain the move. Of 736 grid applications filed from August 2024 to March 2026, 71% were for the capital region, and only about 1 gigawatt of the 33.6 sought there won approval. Outside it, 187 of 214 cleared the first review. Korea wants 8.4 gigawatts of AI capacity by 2029.
Established
- The notice is dated November 20 and closes December 30.
- Non-capital facilities at 50 megawatts contracted power or less are exempt.
- Colocation facilities count as AI data centres under the act.
Not established
- That it is law. A legislative notice is a draft text.
- The special zones. None are designated, and that rule is still planned.
- That power arrives. Exemption from review is not a grid connection.
The five-minute readThe record, the timeline, the weight and 4 sources
The record
The Ministry of Government Legislation's register carries the notice: "Notice of the proposed enactment of the Enforcement Decree of the Act on Promotion of the AI Data Center Industry", law type presidential decree, issuing ministry the Ministry of Science and ICT, start date November 20, 2026, end date December 30, 2026, record 89548. The ministry's own account, carried by Korean outlets the same day, sets out the content. Facilities built, expanded or converted outside the greater Seoul area with contracted power of 50 megawatts or less are excluded from the power system impact assessment. The ministry says it weighed industry requests against the effect large sites have on regional power systems, and rejected a 100 megawatt threshold on the ground that even at that level most gigawatt-scale projects would still fall outside the exemption. Colocation facilities, which provide space, power, telecommunications and cooling for equipment owned by other operators, are brought inside the definition of an AI data centre under the act. A fast-track gives priority assessment to megaprojects and to sites applying for bundled permitting. The bundled permitting clock: the ministry requests review from relevant agencies within 7 days, agencies reply within 10 days on whether documents need supplementing, and the ministry completes its review within 30 days and refers the case to the National AI Strategy Committee. If an agency misses its deadline the process proceeds on the documents filed. A public hearing is set for December 9 in Mapo-gu, Seoul. Planned but not in the draft: exemption from the non-technical part of the assessment inside designated special zones, which requires the climate ministry to revise its own notice. Not established: how many zones, where, or when the decree takes effect.
How it got here
- Sep 14
Korea Electric Power asks Samsung Electronics and SK hynix for 25 trillion won up front to build the grid they will need. Edition 021's card.
- Oct 23
The government signals it will cut AI data centre rules and designate special zones next year, the first public sign of the direction this decree takes.
- Nov 16
North Carolina moves the other way, making large data centres sign 15 years and pay for power they do not use. Edition 099's compute card.
- Nov 20
The Ministry of Science and ICT files the legislative notice. Comment closes December 30, with a hearing on December 9 and a local coexistence guideline promised for the first half of 2027.
The Ministry of Climate, Energy and Environment, which owns the assessment and must revise its own notice; Korea Electric Power, which carries the connection cost; the National AI Strategy Committee, now referee on bundled permits; the colocation operators just brought inside the act; and the provinces that will host unstudied sites.
What to watch
- Would strengthen itThe decree is promulgated with the 50 megawatt exemption intact, or the climate ministry revises its notice to exempt special zones from the non-technical assessment, by June 30, 2027.
- Would weaken itThe comment period closes on December 30 and the enacted decree drops or lowers the 50 megawatt exemption, or no decree is promulgated, by September 30, 2027.
- Would strengthen itKorea reports more non-capital AI data centre approvals in the 6 months after enactment than in the 6 months before, by December 31, 2027.
Why it weighs this much
Cost is low: filing a legislative notice costs a ministry almost nothing, and no money moves. Commitment is medium, the honest reading of a dated official text that is not yet law. The register entry, the named ministry, the 40-day comment window and a scheduled hearing are harder to walk back than a speech, and the ministry published its reasoning for choosing 50 rather than 100 megawatts. Reversibility is high: a draft decree can be amended or dropped, and the special zone exemption depends on a second ministry acting. Persistence is years if enacted, because permitting rules outlast the projects they clear. We score this modestly on purpose: it is a real action, and a proposal.
The words
- Power system impact assessment
- Korea's mandatory study of what a large electricity user does to the grid. Passing it is a precondition of connection, and it is where projects wait.
- Contracted power
- The maximum electricity a site agrees to draw under its supply contract. It is the number the threshold is measured against, not actual use.
- Legislative notice
- The comment stage for a Korean decree. The text is official and dated but not yet law, and it can change before enactment.
- Colocation
- A data centre that rents space, power and cooling to operators who own the servers. Including it widens who the act supports.
Sources
- MMinistry of Government Legislation register: legislative notice of the AI Data Center Act enforcement decree, Nov 20 to Dec 30, 2026moleg.go.kr
- FFinancial News: the 50 megawatt exemption, colocation, and the 7, 10 and 30 day permitting clock, Nov 20, 2026, 13:41 KSTfnnews.com
- AAju Press: draft decree released for comment, fast-track for gigawatt projects, grid application figures, Nov 20, 2026, 12:39 KSTajupress.com
- KKyunghyang Shinmun: ministry reasoning on 50 against 100 megawatts, special zones, Nov 20, 2026, 15:33 KSTkhan.co.kr