Confirmed 16 Nov 2026 · Governance A one-minute read

North Carolina made big data centres sign 15 years and pay for unused power.

The commission issued the orders on November 16, covering data centres above 100 megawatts at 75% minimum billing. Duke disclosed them on November 17 and is still assessing the schedule.

Until now

Data centres negotiate power contracts privately, on terms nobody outside the room sees.

Now

A state published the terms, and 15 years of minimum payments is one.

Why it matters

A 75% minimum on a 15-year contract turns a tenant's option into an obligation. Duke has 6.7 gigawatts under signed agreements, 92% of it data centres. The one protection against plants outliving tenants, the stranded generation charge, has no methodology yet.

Established

  • Minimum 15-year contracts for data centres above 100 megawatts, with 75% minimum billing demand.
  • A letter of credit covers all transmission network upgrades; early termination carries liquidated damages.
  • Duke says it is still assessing that portion of the orders.

Not established

  • What the stranded generation charge costs. Its methodology is to be determined.
  • The transmission cost split. That methodology is also undetermined.
  • That any tenant signs. The schedule governs contracts not yet written.
The five-minute readThe record, the timeline, the weight and 6 sources

The record

Duke Energy Corporation filed a Form 8-K on November 17, 2026, period of report November 16, under Items 8.01 and 9.01, for 3 registrants: Duke Energy Corporation, Duke Energy Carolinas and Duke Energy Progress. Read at sec.gov. It states that on November 16, 2026 the North Carolina Utilities Commission issued written orders approving the Comprehensive Revenue Requirement Settlements, filed July 17 and August 5, 2026 against applications of November 20, 2025. Approved: return on equity of 9.8% on a 53% equity component, against 10.95% requested and 10.48% in rebuttal; North Carolina retail rate bases of about $25.7 billion for Duke Energy Carolinas and $17.8 billion for Duke Energy Progress; 2-year revenue increases of $496 million and $338 million, averaging 3.7% and 3.4% a year, against $1,002 million and $729 million originally sought; multi-year plan capital of about $3.8 billion and $3.4 billion; rates effective January 1, 2027; a possible stay-out barring a base rate case before November 1, 2028; one-time pre-tax charges of $10 million each in the fourth quarter of 2026. Exhibit 99.1 is the Duke Energy Carolinas fact sheet, docket E-7 Sub 1329. Its DC Schedule terms, quoted: "Minimum 15-year contract terms for data centers >100 MW", "Minimum billing demand of 75% of contract demand", "Interim curtailment provisions", "Contribution in Aid of Construction (CIAC) for dedicated facilities", "partial direct assignment of transmission network upgrades based on customer benefit", "Letter of Credit for all transmission network upgrades", "Liquidated damages for early termination", and "A stranded generation charge requiring security posting and additional payment" at contract expiry "using a methodology to be determined in the future". Exhibit 99.2 carries the same DC terms for Duke Energy Progress. The 8-K itself says only that the orders "establish a DC Schedule applicable to certain data center customers", that Duke is "still assessing that portion of the Orders", and that there are "no material changes to the Comprehensive Settlements". Duke's release, 10:10 Eastern Time on November 17, describes a 50 megawatt threshold, upfront dedicated-facility payments and security requirements. Secondary reporting puts the stranded generation charge at $67,357 per megawatt-year off a proxy combined cycle unit with a 35-year life, and counts 7.9 gigawatts of large load in advanced development with 6.7 gigawatts under signed energy service agreements from March 2024 to April 2026, 92% data centres. Neither figure is in the exhibits.

How it got here

  1. Nov 20 2025

    Duke Energy Carolinas and Duke Energy Progress file rate and performance based regulation applications, seeking about $1,002 million and $729 million over 2 years at a 10.95% return on equity.

  2. Sep 16

    The House votes 417 to 3 to make data centres pay for the transmission lines built to serve them. Edition 024's governance card.

  3. Sep 18

    Virginia signs an order making large data centres harder to build there and sets up a state review. Edition 026.

  4. Nov 3

    Voters in 10 states decide 41 data centre ballot measures, and 28 of them would limit data centres. Edition 072.

  5. Nov 16

    The commission issues written orders in docket E-7 Sub 1329 and its Duke Energy Progress companion, approving the settlements at 9.8% and establishing the DC Schedule.

Who has to react

Duke Energy, which says it has not finished reading the schedule; the developers behind 6.7 gigawatts of signed agreements; Amazon, Microsoft, Google and Meta, all building in the Carolinas; the Public Staff, which must finalise the numbers with Duke; and commissions in Virginia, Georgia, Ohio and Texas now holding a published template.

What to watch

  • Would strengthen itA utility commission outside North Carolina approves a data centre tariff with a minimum term of 10 years or more and a minimum billing demand, or cites these orders, by June 30, 2027.
  • Would weaken itThe stakeholder process closes with no stranded generation methodology set, or the commission removes or suspends the stranded generation charge, by December 31, 2027.
  • Would weaken itDuke files a data centre service agreement under the DC Schedule with a term under 15 years or a minimum billing demand under 75%, or the orders are stayed on appeal, by June 30, 2027.

Why it weighs this much

Signal strength
CostMedium
CommitmentHigh
ReversibilityLow
PersistenceStructural

Cost is medium. A commission spends process, not money, and Duke took a return on equity 115 basis points below its request. Commitment is high: written orders in a contested docket, disclosed by the utility in a Form 8-K, with rates effective January 1. Reversibility is low. Rate orders are appealed, not withdrawn, and the 15-year minimum binds every contract signed under it. Persistence is structural: once a state publishes terms for data centre service, those terms become what other states argue about.

The words

Minimum billing demand
The floor on your bill. At 75% of contract demand you pay for three quarters of the power you reserved, used or not.
Stranded generation charge
A payment covering power plants built for a customer who leaves before the plant is paid off. Here the amount is not yet set.
Contribution in aid of construction
Cash the customer hands the utility up front to build the wires and equipment dedicated to it, instead of spreading that cost across all ratepayers.

Sources

Your call

Which explanation do you believe?

A call is final. Other people's calls show after yours.

8 contributions. Thank you.

You have built
a record here.

Keep it: create an account to verify your contributions and put your name to the answers you choose. Your record stays yours.

Keep my record ↗
Optional: help show whose perspectives are missing
Kept with your answers under a random id, never with your name. Used for one thing: showing you, on your record, where you stand next to people like you, once at least 20 of them have answered.

Add your signature

Stand behind your judgment.

Create an account to attach your name to this answer. Your other answers show no name unless you sign them too.

Sign up to add your name ↗

Already have an account?