Confirmed 21 Oct 2026 · Infrastructure A one-minute read
NEXTDC cut next year's earnings guidance by A$140 million and froze all new projects.
Power works at its Melbourne data centre are suspended until at least February 2027, so the company removed those contracts from guidance. Its shares fell 37.47% on resuming trade.
The grid delay would cost one site some earnings for one year.
It stopped the company's whole building programme and reset its capital plan.
Why it matters
Citi had put A$25 million of 2027 earnings at risk. The company took out A$140 million, 5.6 times that, and halted every new development and land purchase for the foreseeable future. A planning decision now waits on a state election. Analysts were pricing a delay; the company priced a stop.
Established
- Revenue guidance fell to A$475 to A$500 million from A$615 to A$640 million.
- All new development projects and land acquisitions are on hold indefinitely.
- Jemena does not expect to resume the 66,000 volt works before February 2027.
Not established
- When M3 gets more grid power. The 2028 financial year is Jemena's estimate.
- What the affected contracts are worth. No customer is named.
- Any write-down. The property fair value effect is not quantified.
The five-minute readThe record, the timeline, the weight and 5 sources
The record
NEXTDC published the announcement as an EQS ad-hoc release at 23:39 central European time on October 20, 2026, under article 17 of the European market abuse regulation. The Australian Securities Exchange release is dated October 21, 2026, with an investor briefing at 9:30am. We read the company's own release text, not the exchange PDF. Guidance for the year to June 30, 2027: net revenue A$475 million to A$500 million, from A$615 million to A$640 million; underlying earnings before interest, tax, depreciation and amortisation A$245 million to A$265 million, from A$385 million to A$410 million. The August 27, 2026 guidance included about A$140 million of each from the affected M3 contracts, now excluded until their contribution can be estimated. Capital expenditure guidance falls to A$4,500 million to A$5,000 million from A$5,250 million to A$5,750 million. The new figure includes about A$500 million of reimbursable customer fitout and about A$230 million of capitalised interest the old one excluded, a like-for-like cut of about A$980 million. Jemena Electricity Networks suspended parts of its 66,000 volt line augmentation works in September 2026, citing community and stakeholder opposition, safety concerns and the local council withholding consent as road authority. It does not expect to resume before February 2027, and estimates the next increase in grid supply at M3 falls in the 2028 financial year. Later increases depend on Brooklyn Terminal Station transformer projects, the first now later than planned. Planning application PA2604231 for M3 stages 6 and 7, lodged February 2026, is not expected to be decided until 2027, given caretaker conventions from November 3, 2026 and the Victorian election on November 28, 2026. All new development projects and land acquisitions are on hold for the foreseeable future, uncontracted projects are paused, and the board will evaluate selling sites. Liquidity at September 30, 2026 was A$8,675 million, A$1,275 million of it cash. Covenants require gearing of 60% or less and interest cover of 1.5 times; the company says it complies. A capital review will be announced by the annual general meeting on November 20, 2026. Reported, not read by us: shares fell A$3.44 to A$5.74, a low of A$5.07, on more than 33 million shares against A$9.18 when they last traded, cutting market value to about A$4.4 billion from A$7 billion. Not published: any megawatt figure, any customer name, any contractual penalty, or the fair value effect, which falls to the December half-year results.
How it got here
- Aug
Jemena and Powercor warn that data centres in Melbourne's west are seeking more power than the grid can supply. NEXTDC issues 2027 guidance on August 27 including about A$140 million each of revenue and earnings from the M3 contracts now withdrawn.
- Sep
Jemena suspends parts of the 66,000 volt works, citing community and stakeholder opposition and the absence of council consent as road authority.
- Oct 19
NEXTDC asks the Australian Securities Exchange to halt trading in its shares under listing rule 17.1, pending a material update on the M3 power delay. Edition 056's lead card, the parent of this one.
- Oct 21
Guidance cut, capital expenditure cut by about A$750 million, all new developments and land acquisitions frozen, capital recycling under evaluation, shares resume and fall 37.47%.
The M3 customers, whose contracts left guidance; Jemena and the council that withheld consent; the Victorian government, whose election now gates a planning decision; NEXTDC's lenders and convertible note holders, against covenants of 60% gearing and 1.5 times interest cover; Citi, whose A$25 million estimate was out by 5.6 times; every Australian operator selling capacity it has not energised.
What to watch
- Would strengthen itAnother listed data centre operator cuts guidance or delays a site citing grid connection or network works, by June 30, 2027.
- Would strengthen itThe November 20, 2026 capital review announces a site sale, an equity raise, or a further capital expenditure cut not attributed to M3.
- Would weaken itJemena resumes the 66,000 volt works by February 28, 2027 and NEXTDC restores the withdrawn contracts to guidance by June 30, 2027.
Why it weighs this much
Cost is high: about A$140 million each of revenue and earnings withdrawn, about A$750 million of capital spending deferred, and about A$2.6 billion of market value gone in an afternoon. Commitment is high because a guidance revision is a formal disclosure a listed company cannot quietly walk back, and freezing land acquisitions is a decision the board has to defend at its November 20 meeting. Reversibility is hard near term: the company controls neither the pole route, the council consent nor the election timetable. Persistence is years, not structural: the works can resume and the capacity is built. What is lost is the year it was sold in.
The words
- Guidance
- A listed company's own published forecast of its revenue or profit. Changing it is a formal market disclosure, not an opinion, which is why a cut moves the share price.
- Line augmentation
- Building or upgrading the poles, wires and transformers that carry electricity to a site. It needs land access and council consent, which a data centre customer cannot supply.
- Caretaker conventions
- Rules that stop a government making significant decisions in the run-up to an election. They can freeze planning approvals for weeks.
Sources
- ANEXTDC EQS ad-hoc release: M3 Melbourne Power Delay and Revised FY27 Guidance, Oct 20, 2026ad-hoc-news.de
- FSame release via Finanzwire, with the full guidance tables and Jemena detailfinanzwire.com
- IIBTimes Australia: share price, intraday low, volume and Citi comment, Oct 21ibtimes.com.au
- CCNBC: NextDC shares plunge after it slashes earnings forecast, Oct 21, 2026cnbc.com
- WW.Media: NextDC cuts FY27 guidance, pauses new projects over M3 power delayw.media
Your call
Which explanation do you believe?
A call is final. Other people's calls show after yours.